The main switchboard is a bus with breakers on it. Generator breakers put power on; feeder breakers take it off. The tie breaker splits the bus into two halves so that a fault on one half does not take the whole ship, and so that one half can be worked on. Every feeder breaker protects one cable and whatever hangs on the end of it: a single large motor, a group starter panel full of small ones, a transformer to the 220 V side, a distribution board. The drawing to carry is the one-line with each feeder named, because the first question on any trip is what else just lost power, and the second is where the upstream breaker is.
Inside each feeder cubicle there is more than a breaker: current transformers for the ammeter and the overcurrent protection, a control transformer, auxiliary contacts that report breaker position to the alarm system, and on the bigger feeders an undervoltage release that opens the breaker on a blackout so the load does not come back on all at once.
Pocket rules. Know the one-line cold. A feeder trip is a fault downstream until proven otherwise; walk the cable before you re-close. Both halves of the board are live with the tie open; the warning plate means it.
Electrical or mechanical. The board, every breaker, every relay, every CT: electrical. Breaker overhaul on a big air circuit breaker: vendor, on a schedule. Changing a setting: only with the go-ahead and the coordination study.