7.3 · (F) A job you do with your handsBattery load test and replacement

Slide the drawing sideways, or open it full size.
Battery load test and replacement
Figure 7.3. Battery load test and replacementOpen full size

Load test. Put the real load on the bank: start the emergency generator on it, run the radio station on it, run the emergency lighting on it. Log the voltage at the start, at intervals, and at the end of the required time, and compare the curve with the last test. A bank that sags early and recovers is weak; one that falls off and does not recover is done. Where a real load is not possible, a load bank or a carbon pile tester at the bank's rated discharge for the manual's time does the same job. Specific gravity on open cells tells you the state of each cell, and one low cell is the one that will fail the test next time.

Replacement. Same chemistry, capacity, voltage and physical size; mixing old and new blocks in one bank shortens the life of the new ones. Charger off the bank, cables marked, blocks changed with the bank isolated from its load if the load can stand it. If it cannot, the charger or a parallel string carries the load while the blocks are changed, because taking any block out of a series bank opens the string. Clean and grease the terminals, torque them, write the date on every block, reconnect the charger, check it goes to boost and then settles to float. Old batteries go ashore as hazardous waste, logged.

Pocket rules. Real load, logged, compared. One low cell is next month's failure. Same chemistry, same age. Date the blocks.

Work it

Built for this entry. Lessons first, then the simulator for free play.