3.2 · (R) Yours: something you are responsible forThe emergency board and the bus tie

Slide the drawing sideways, or open it full size.
Emergency board one-line, with its indicating lamps (lamp list from a real board)
Figure 3.2. Emergency board one-line, with its indicating lamps (lamp list from a real board)Open full size

The emergency switchboard is a small copy of the main board with one extra rule: it must never be without power. In normal running it is fed from the main board through the tie, and the emergency generator sits idle. On a blackout the undervoltage relay opens the tie, starts the set and closes its breaker, as 2.5 describes. The interlock between the tie and the generator breaker is the most important interlock on the ship, because closing both would parallel an unsynchronized set with the main bus.

The feeders tell you what the regulations think the ship cannot lose. Read the list; it is a good description of your job's priorities. Everything on this board gets your attention first on day one and first after any blackout.

Pocket rules. The emergency board is never dead by design; if it is, something has failed twice. After any blackout, confirm the tie closed again and the set is back in standby.

Electrical or mechanical. All electrical. The blackout test that proves the tie-and-set sequence: scheduled with the engineer in charge.

Work it

Built for this entry. Lessons first, then the simulator for free play.

All of Part 3