Shore power is one more source with one more breaker, and the board must never let it parallel with a generator unless it was built to. Three things get checked before that breaker closes: rotation, voltage, and whether the pier can actually carry the load you are about to hand it.
Rotation first, every time, even on the pier you used last month; if it is wrong, every motor on the ship runs backward, and the fix is the phase-reversing switch in the shore box if the ship has one, or swapping two conductors at the shore connection, never inside the ship's own wiring. Voltage and frequency next. US piers give 450 or 480 V at 60 Hz; 480 is more than 6 percent over the ship's rating, the most its equipment is built to take steadily, so the engineer in charge decides. Much of the rest of the world gives 400 V at 50 Hz, which a 60 Hz ship cannot use without a frequency converter, on the pier or aboard; a transformer changes the volts, not the hertz. Capacity last: the pier breaker and the cable are the ceiling, and a reefer deck will find it.
Expect the insulation monitor to drop to zero the moment you connect, unless the ship takes shore power through its own isolation transformer. The pier's neutral is tied to ground and the hull is tied to the pier, so the monitor reads the pier's ground; the three lamps usually stay even, because that neutral holds every phase at the same voltage to the hull. It clears when the shore breaker opens. Remember what it means while it lasts: on shore power the ship is a grounded system, and a first ground is a short that trips a breaker, not a lamp. Changeover on an older board means a blackout: generator running, bridge told, open shore, close generator. On a board with a synchronizer, it is 2.3 again: rotation proven, matched, closed with the needle slow.
Pocket rules. Rotation, then voltage, then close. Expect the insulation alarm on shore power. Never swap phases on the ship's side. A warm lug after an hour is a loose lug.
Electrical or mechanical. The box, the breaker, the checks, the changeover, the lugs: electrical. The cable and everything upstream: the pier. Whether to black out to change over: the engineer in charge decides.