5.8 · (R) Yours: something you are responsible forThe PLC: power, CPU, I/O, program, and what the lights mean

Slide the drawing sideways, or open it full size.
A PLC rack and what its lights mean
Figure 5.8. A PLC rack and what its lights meanOpen full size

A PLC is a relay panel that moved into a box. Power supply, a processor running a program, input cards that turn field contacts and signals into bits and numbers, output cards that turn bits back into contacts and signals, and a communication port to a screen or a network. You will find them in purifier controllers, boiler controls, crane cabins, hatch cover and ramp systems, the engine safety system, and increasingly inside the switchboard.

The lights are the first diagnostic and the most ignored. On the CPU: power, run, fault, battery. On every I/O card: one LED per channel, lit when the input is on or the output is driven. A sensor that is made and an input LED that is dark means the problem is between the sensor and the card (wiring, power, sinking/sourcing, 1.12) or, less often, a failed input channel: 24 V on the terminal with the LED dark is the card, 0 V is the field. An input LED lit and the program not acting on it means the program or the card's address. An output LED lit and the coil not pulling in means the card's own output, the output group's supply fuse, the wiring or the coil. An output LED dark when it should be lit means the program has not been told what it needs to be told; go back to the inputs it is waiting for. That one habit, reading the LEDs against the drawing, finds most PLC faults without a laptop.

The backup battery holds the program and the clock on older units. It has a date on it and a low-battery LED, and when it dies the program goes with it on the next power cycle, so there must be a backup of the program somewhere you can find.

Pocket rules. LEDs first, laptop second. Input dark with the sensor made: field wiring, or the channel if the terminal has volts. Output lit with nothing happening: the card's output, its supply, or the field wiring. Output dark: find the input it is waiting for. Know where the program backup lives and when the battery dies.

Electrical or mechanical. Power, I/O cards, wiring, battery, backups, reading the program: electrical. Changing the program: vendor, or you with the go-ahead and a backup first.

Work it

Built for this entry. Lessons first, then the simulator for free play.

LessonThe PLC and What Its Lights MeanNo. 1 hydrophore pump on a PLC: find the power supply, CPU, cards and port; read the LEDs through a good cycle; four mornings split by the lights; an input proved with the meter; five calls.LessonSwap a Card, Force a Point, Back Up and RestoreNo. 1 hydrophore pump’s PLC: back up before you touch, swap a dead output card with its block still wired, set a new card’s address, force a failed float and clear it, restore after a flat battery.Simulator · free playFault BenchStarters with a fault you cannot see: operate them, read volts, ohms and amps on any terminal, find the fault, fix it and prove it. Twelve circuits (across-the-line pump, hold bilge pump on floats, wye-delta, a standby pump that starts on low pressure, a starting air compressor with its unloader and trips, and the sewage plant three ways: on floats with its blower, and two timer-run plants; the engine room crane hoist, reversing, with its limits and brake; a generator breaker's closing and tripping circuits in TEST; and an alarm system cabinet with two 4–20 mA loops and two switch inputs; and a hydrophore pump run by a PLC, where the program is your meter) and 250 faults at random.Simulator · free playPLC ProgrammerLearn to write ladder logic from zero. Follow along: twenty-two short guided exercises that tell you exactly what to press, from what a PLC is to contacts, coils, branches, the seal-in, NC wiring, the scan, memory bits, timers, latches, counters, the one-shot, alarm logic, numbers and math, 4–20 mA scaling, an analog alarm with a deadband, a step sequence, and the watch and force tables; skip any you know. Then build it yourself: eleven jobs on the ship's machinery, from a starter and a hold bilge pump to wye-delta, run hours, a hydrophore on a pressure transmitter, tank level alarms with a sensor fault and MAC1's auto start sequence, each checked by tests.Simulator · free playPLC RackSinking and sourcing inputs with PNP and NPN sensors, reading a PLC rack's LEDs to split a fault between field and PLC, and the safe order for swapping a card or forcing a point.